Hanford News
Welcome to the Hanford News
Edit Profile
Log Out

Home
News/Archives
Opinions
History
Photos
Press Releases
Documents
Related Links
Contact us
$6.1M in Hanford work awarded
Friday July 30th 2010

12 of 15 Hanford projects on budget and schedule
Friday July 30th 2010

Study: US ability to investigate nuclear blasts fades
Friday July 30th 2010

Safety board schedules vit plant hearings
Thursday July 29th 2010

Intellegration to show off Richland facility today
Thursday July 29th 2010

Print Story

tool name

close
tool goes here
Rail system being built at Hanford vit plant

This story was published Friday March 5th 2010

By the Herald staff

HANFORD -- Work has begun on a custom-designed rail system to safely move samples of radioactive waste through the laboratory at Hanford's vitrification plant.

The Analytical Laboratory will be used to analyze about 10,000 samples annually from throughout the plant as waste now stored in Hanford's underground tanks is turned into a stable glass form for disposal. The samples must be analyzed to ensure the glass meets regulatory standards.

The transportation system being installed now will be used to move high-level and low-activity radioactive wastes through the lab.

"(It) required precision engineering and fabrication and will require the same precision in installation," Heidi Schuette, a deputy project engineering manager for Bechtel National, said in a statement.

A small crane will lift an empty 55-gallon drum onto a cart called a bogie. The bogie will travel on the rail through a door that's shielded to protect against radiation and up through a hatch to the lab's hot cell.

Samples that have been analyzed inside the hot cell will be loaded into the drums using remotely controlled mechanical arms. The drum then will be lowered back through the hatch and into a maintenance area for removal from the lab.

Crews began installing the hatch this week and will continue installing the rails, bogie and shielded door throughout the spring.

Components were made by Premier Technology Inc. in Blackfoot, Idaho.

The Analytical Laboratory, one of the four largest buildings at the $12.2 billion Hanford Waste Treatment Plant, is 320 feet long, 180 feet wide and about four stories high.

"The external structure of the lab was topped off in 2007, and we continue to make significant progress on the interior of the facility," said Raleigh Amos, a Bechtel Hanford superintendent, in a statement. "The installation of the waste-transfer equipment is just another step toward operations in 2019."


Dept. Of Energy: DOE reduces information services in effort to save money

07/27/2010

Fluor: Hanford ships 1,000 pounds of plutonium to New Mexico

04/10/2008

Battelle/PNNL: Senate OKs $20M for PNNL program

07/16/2010

CH2M Hill: About 400 CH2M Hill workers to change shifts

06/25/2010

Washington Closure: Hanford landfill work halted for probe

07/16/2010

Cleanup: 12 of 15 Hanford projects on budget and schedule

07/30/2010

Energy Northwest: Energy Northwest names interim CEO

06/18/2010

B Reactor: DOE endorses Hanford's B Reactor for national historical park

05/21/2010

Vit Plant: Cooling panels being installed at vit plant

07/29/2010


Find a Job
Keywords:
Location:



News | History | Related Links | Opinions

Press Releases | Documents